November 5, 2026
TODAY'S AGENDA
PRODUCT ROADMAP · LATEST (UPDATED 2026-10-29)
US REQUESTS · THE LAST THREE ASKS
Raised in last week's sync and during design discussions. Each entry gives the conclusion, the owner and where it lands.
BATCH 2 · DELIVERY PROGRESS (INTERNAL UAT 11-10)
BATCH 3 CRITICAL PATH · TPO DEVICE PERMISSIONS
Batch 3's biggest delivery risk: blocked from both ends. the design still needs to change, and the US team still needs to agree. | Owner Fan Gong
BATCH 4 PREP · FEATURE ARCHITECTURE & MENU RESTRUCTURE
Owner Frank Jiang · Three foundational documents delivered; the US front line has already given feedback on the personas and use cases.
LAST MEETING · FOLLOW-UPS FROM SYNC #8 (OCTOBER 22)
| Item | Owner | Status | Notes |
|---|---|---|---|
| Create ORs to track alarm management and firmware upgrade | Jeans Huang | Created | Both are out of project tracking, but still need an owner; ORs carry them Alarm Management ↗ · Firmware Upgrade ↗ |
| Phased product release plan (exit criteria + US sign-off owners) | Frank / White | Finalised | See the roadmap earlier; US still needs to name the signer per feature |
| Josh to run the US service team trial of Smart Diagnosis and report back | Josh Brooks | Pending | Agreed at the 10/22 sync: "within two weeks", i.e. ~11/5 (not a hard deadline); no feedback yet |
| Josh to review the product definition and persona documents | Josh Brooks | Feedback in | The US front line has commented; still being consolidated. Documents continue to evolve with detailed design. |
| TPO device permission design review | Fan Gong | SZ done | Shenzhen review complete and now in design & dev; US review awaiting Lun |
| Internal decision on whether metrics go on the roadmap | Frank / Jeans | Replied | Replied to Ronnie: Smart Diagnosis has stats, platform-wide metrics in Batch 4 ClickUp #868mr803y ↗ |
RELEASE PLAN · MILESTONES AND EXIT CRITERIA BY BATCH
Ronnie asked on 10/22: "when do customers first get to use it?" That needs a table, not a sentence.
| Batch | External milestones | Exit criteria | US sign-off owner |
|---|---|---|---|
| Batch 1 | 07.31 released Full rollout by end of Dec |
Diagnostic accuracy accepted; T1 trial passed | To be named |
| Batch 2 | Internal UAT 11.10 Beta 11.15 · Launch 12.30 |
Logs in production; MFA issues cleared on functional permissions; data permissions out of development | To be named |
| Batch 3 | Alpha 11.30 Beta 12.15 · Launch 12.30 |
TPO device permissions pass US review and ship; ChatBI and Smart Assistant usable | To be named |
| Batch 4 | Alpha 01.15 Beta / Launch TBD |
UI/UX revamp and metrics design approved; detailed feature design complete | To be named |
BATCH 1 + 2 · SMART DIAGNOSIS
Owner Jeans Huang · T1 is in scope. What needs settling is how far "all internal accounts" reaches, whether execution rights open with it, and how the frontline actually picks it up.
NEXT STEPS & ACTION ITEMS
Weekly Sync · 2026 年 11 月 5 日
TODAY'S AGENDA · 今天议程
PRODUCT ROADMAP · 最新路线图(2026-10-29 更新)
US REQUESTS · 美方近期提出的三项需求
来自上周例会与设计沟通,逐条给出结论、责任人与落地位置。
BATCH 2 · 交付进展(内部 UAT 11-10)
BATCH 3 关键路径 · TPO 设备权限
Batch 3 里这块风险最高:设计还要改,美方还要认。 | 负责人 Fan Gong
BATCH 4 前置工作 · 功能架构与菜单重构
负责人 Frank Jiang · 三份基础文档已交付,美国一线已对用户与用例文档给出反馈意见。
上次会议 · 第八次周会(10月22日)遗留事项
| 事项 | 负责人 | 状态 | 说明 |
|---|---|---|---|
| 建 OR 跟踪告警管理与固件升级 | Jeans Huang | 已创建 | 两块已移出项目跟踪,但不等于不做,靠 OR 承接 Alarm Management ↗ · Firmware Upgrade ↗ |
| 出分批次产品发布计划(含 exit criteria 与美方 sign-off 负责人) | Frank / White | 本次定稿 | 见上一页路线图,仍需美方确认每个功能的签核人 |
| Josh 组织美国服务团队试用 Smart Diagnosis 并反馈 | Josh Brooks | 待反馈 | 10/22 会上约定「两周内」,折算约 11/5(非硬截止),目前未收到反馈 |
| Josh 审阅产品定义与用户画像两份文档 | Josh Brooks | 已有反馈 | 美国一线已提出反馈意见,正在收敛;文档随详细设计继续补充 |
| TPO 设备权限设计评审会 | Fan Gong | 深圳完成 | 深圳内部评审已完成并进入设计开发,美国评审待 Lun 安排 |
| 内部讨论埋点是否纳入 roadmap | Frank / Jeans | 已回复 | 已回复 Ronnie:智能诊断现有统计,全平台埋点进 Batch 4 ClickUp #868mr803y ↗ |
RELEASE PLAN · 各批次发布节点与准出条件
Ronnie 在 10/22 问的是"客户什么时候第一次能用上"。这个问题一句话答不了,需要一张表。
| 批次 | 对外节点 | 准出条件(exit criteria) | 美方 sign-off 负责人 |
|---|---|---|---|
| Batch 1 | 07.31 已发布 全量铺开至 12 月底 |
诊断准确率验收、T1 试用通过 | 待美方指定 |
| Batch 2 | 内部 UAT 11.10 Beta 11.15 · Launch 12.30 |
日志管理上生产;功能权限 MFA 问题清零;数据权限完成开发 | 待美方指定 |
| Batch 3 | Alpha 11.30 Beta 12.15 · Launch 12.30 |
TPO 设备权限美国评审通过并交付;ChatBI 与智能助手可用 | 待美方指定 |
| Batch 4 | Alpha 01.15 Beta / Launch 待定 |
UI/UX 改版与埋点方案评审通过;功能架构详细设计完成 | 待美方指定 |
BATCH 1 + 2 · SMART DIAGNOSIS
负责人 Jeans Huang · T1 也在开放范围内。要定的是账号覆盖多大的范围、执行权限是否同步放开、一线怎么用起来。
NEXT STEPS & ACTION ITEMS · 下一步计划